Fjord moorings for Hywind Tampen floating wind turbines

Acteon provided several pre-lay mooring systems. All four wind turbines were connected to the prelay mooring spreads in September 2022 and were secured to the moorings until the units were towed to Tampen Field and installed offshore with the other seven units.

Case Studies

05 Apr 2023

Integrated solution for installation of over 300 piles on major wind farm

Discover how Acteon deployed an integrated solution to monitor and install 349 piles, 111 WTG jackets, and 2 OSS jackets at a major Southeast Asia wind farm.

Case Studies

20 Mar 2023

Efficient structural monitoring measurement campaign on the TetraSpar Floating Wind Demonstration Project

Acteon’s Geo-services business line was contracted to provide structural monitoring services for the TetraSpar Floating Wind Demonstration Project.

Case Studies

27 Feb 2023

Fécamp Offshore Wind Farm GBS settlement monitoring

Discover how Acteon enabled the safe, accurate installation of 71 offshore wind turbine foundations at Fécamp using real-time GNSS tracking, seabed monitoring, and custom-fit technology; ensuring stability, reducing risk, and enhancing project confidence.

Case Studies

05 Jan 2023

Chain removal completed on a major platform without the use of an AHV

Intermoor safely removed 5,200-ft of mooring chain from a floating production unit in ultra-deep water, without an anchor handling vessel - cutting complexity, cost, and risk.

Case Studies

07 Nov 2022

FPU tow-out and hook-up support for Subsea 7

Acteon supported the safe transit of King’s Quay FPU with real-time GPS tracking, hazard surveys, and offshore hook-up. Seamless execution, zero downtime.

Case Studies

25 May 2022

Subsea cable survey and monopile inspection for Coastal Virginia Offshore Wind

Acteon supported Dominion Energy with high-res cable and monopile inspections offshore Virginia, enabling safe expansion of its 2.6 GW wind farm development.

Case Studies

25 Feb 2022

Pioneering steel lazy wave riser monitoring system to combat slugging fatigue in ultra-deep water

Acteon’s Geo-services business line, was commissioned to deliver a tailored monitoring solution to an operator in South America to understand the mechanics of their steel lazy wave riser (SLWR) response to slugging, to benchmark multi-phase flow predictions and riser fatigue predictions.

Case Studies

15 Dec 2021

Volumetric surveys to enable future planning in remote areas

UTEC, Acteon’s Geo-services business line, was contracted to provide a bathymetric and topographic survey at Loch A’Chuilinn and Loch Achanalt.

Case Studies

01 Dec 2021

Radar surveys increase efficiency on Berwick Bank wind farm development

UTEC, was commissioned by SSE Renewables to undertake topographical and ground-penetrating radar surveys for the cable landfall areas of the Seagreen Windfarm (now Berwick Bank)

Case Studies

29 Nov 2021

Efficient mooring chain inspection and replacement for FPSO in UK North Sea

Intermoor delivered a full-scope mooring chain inspection and replacement for the Global Producer III FPSO in the UK North Sea, overcoming marine growth and tight timelines to ensure safe, DNV-compliant execution.

Case Studies

22 Jul 2021

Successful nearshore mooring installation near Indonesian shoreline

The rigid reel lay vessel was to be moored at BOMC for reeling operations. Using their experience in mobile and permanent mooring installation, Intermoor, Acteon’s Moorings and Anchors business line, had to consider several challenges during the planning and operations stage.