Intermoor, Acteon’s Moorings and Anchors business line, has successfully installed and hooked up a permanent mooring system for the Delta House field floating production system (FPS) in the Gulf of Mexico. The mooring lines were deployed and installed on time and without incident, despite the challenging circumstances. 

Project developer LLOG Bluewater, a joint venture between LLOG Exploration and Blackstone Energy Partners and its affiliates, contracted Intermoor  

  • To design, fabricate and install 12 suction piles anchors;
  • to install 12 preset chain/polyester mooring lines;
  • and to hook up the FPS in 4450 ft of water in the Mississippi Canyon Block 254, 130 miles southeast of New Orleans. 

Intermoor fabricated the suction piles at its 34-acre facility in Morgan City, Louisiana, USA. The piles, which were used as permanent anchors for the project, are 85 ft long, 16 ft in diameter and weigh approximately 165 metric tonnes. Installation was in Q2 2014 and was followed by the hook-up in Q3 2014. 

Adaptability to optimise deepwater mooring installation

One of the challenges of this deepwater installation was the use of a prescribed anchor-handling vessel, the Joshua Chouest, on a long-term charter to the LLOG drilling department. Because the mooring system was procured early in the design process, it was necessary to find a solution that would utilise the selected vessel and extend the vessel capabilities beyond what has previously been done with this class of vessel in terms of mooring component size. 

The Project Manager at Intermoor said, “Fixing two elements, the vessel and the mooring components, in the design, independently of one another, was challenging. However, working closely with the suppliers and manufacturers in an iterative process meant that we could ensure the equipment was optimised for the application and the project was successful. 

“As permanent mooring systems get larger and larger, utilising traditional anchor-handling vessels for the installation is proving more and more challenging. Flexibility, adaptability and innovation are critical to extending the capabilities of the existing fleet of anchor-handling vessels to keep pace with the larger mooring components, to maximise returns and deliver projects on time and within budget constraints,” he added. 

The Delta House mooring system was deployed and installed safely and on time. The hook-up system was successfully connected under high loads, with close attention to tolerances and connection interfaces. Technical innovations  

  • stretched the capabilities of the designated anchor handling vessel,
  • minimised twist in the mooring,
  • and ensured cost-effectiveness that would not have been possible with another vessel. 

The FPS is designed for a peak capacity of 100,000 bbl./d of oil and 240Mcf/d of gas. First production from this facility is expected in the first half of 2015.

Related articles

Discover the latest mooring solutions articles from Acteon

News

19 Jan 2026

ARC grant secured for groundbreaking plate anchor research

Intermoor, Acteon’s Moorings and Anchors business line, is proud to announce that the pioneering “SEPLA in Sand” project, developed in collaboration with researchers from The Centre of Offshore Foundation Systems at the University of Western Australia (UWA), has received a major grant from the Australian Research Council.

News

02 Dec 2025

Acteon inks three-year Petrobras contract for enhanced mooring asset integrity

Intermoor, Acteon’s Moorings and Anchors business line, has been awarded a three-year contract by Petrobras, following a Memorandum of Understanding (MoU) signed at the Offshore Technology Conference (OTC) in Houston in May 2025. 

News

03 Nov 2025

FEPLA advances: First geotechnical tests validate offshore solution

Intermoor, Acteon’s Moorings and Anchors business line, has completed the first phase of model testing for its Flexibly Embedded Plate Anchor (FEPLA) at the University of Dundee Geotechnical Engineering Facility.

Speak to our team

Our team of experts will design a solution that fits the technical, environmental and commercial demands of offshore projects.