SURF installation completed ahead of schedule during monsoon season

18 May 2020 1 minute 30 seconds

Mampu cable transfer between two offshore vessels

Project overview

Project name

Mampu-1 FPSO ESP Installation

Location

AJK Field, Sarawak, offshore Malaysia

Developer partners

MISC Offshore Floating Terminals Dua Ltd (MOFT2), a subsidiary of MISC Berhad

Intermoor, Acteon’s Moorings and Anchors business line, was contracted for the installation of several structures on MAMPU-1 FPSO and adjacent platform.

Congested seabed, monsoon and short project timeline 

The project was awarded in August and the vessel mobilisation was planned for early November, which gave the project team a limited timeline to ensure offshore readiness for operations.

The work also took place in a very congested subsea environment: the ESP module target landing area at MAMPU-1 was surrounded by production piping, existing bulky structures, and supports which allowed for minimal excursions during the lifting. Finally, offshore operations had to occur during the high-risk monsoon season in Malaysia.

Reliable offshore execution through expert planning 

Extended working hours were put in place to meet the tight completion target dates. 

The engineering team addressed difficult offshore conditions issues by incorporating additional safety factors into their engineering work including factoring in the most drastic weather conditions into the design to cover all possibilities. A tugger winch and tag lines were used in a mandatory fashion to minimise any movement during installation due to challenging offshore conditions such as sea swell, wind, and vessel pitching. 

The team also added alternative routes and scenarios to the offshore procedures and manpower during the offshore installation. They used their long-standing experience with floating assets to ensure careful planning and increased coordination. 

The scope of work included: 

  • Project management
  • Engineering
  • Offshore operations for the installation of:
    • One electric submersible pump (ESP) power generation module on FPSO
    • One chute support structure at the Tarpon platform
    • One shelter structure at the Tarpon platform
    • 1.26 km of subsea power cable between FPSO MAMPU-1 and Tarpon platform. 

A fully integrated delivery

Several Acteon business lines have come together on this project, to provide all necessary work to install the ESP system. Whilst Intermoor provided a single interface engineering and project management team, they also utilised UTEC for survey work. 

As part of the integrated service, Intermoor also chartered a construction support vessel for the core installation and an anchor-handling tug and barge for the transport of the module and structures. 

The work was completed ahead of schedule and without any lost time incidents.

Related case studies

Discover more mooring solutions projects

Case Studies

25 Jan 2025

Dual FPSO installation of driven and suction pile mooring systems offshore China

Intermoor delivered a complex mooring campaign for two FPSOs offshore China, installing 25 mooring lines and suction piles under tight weather windows and Covid-19 restrictions.

Case Studies

03 Jun 2023

Fjord moorings for Hywind Tampen floating wind turbines

Acteon provided several pre-lay mooring systems. All four wind turbines were connected to the prelay mooring spreads in September 2022 and were secured to the moorings until the units were towed to Tampen Field and installed offshore with the other seven units.

Case Studies

05 Jan 2023

Chain removal completed on a major platform without the use of an AHV

InterMoor safely removed 5,200-ft of mooring chain from a floating production unit in ultra-deep water, without an anchor handling vessel - cutting complexity, cost, and risk.

Speak to our team

Our team of experts will design a solution that fits the technical, environmental and commercial demands of offshore projects.