Project overview

Project type

Offshore platform foundation grouting

Location

North Sea

Solution

  • Recirculating jet mixing & pumping system
  • Portland cement grout
  • DNV-certified full cement silos 

Menck, Acteon’s Marine Foundations business line, delivered offshore grouting services to install a wellhead platform foundation and four-legged jacket with driven foundation piles in the North Sea. 

The challenge  

Together with our partner we had to rapidly develop and approve a grout mix design and prepare the full equipment spread within tight schedule constraints ahead of offshore operations. 

Seamless offshore grouting solution 

We leveraged our laboratory, supply chain, and equipment capabilities to deliver a high-quality, bonded grouted connection between the jacket, topside, and foundation piles. A grout mix was pre-designed and validated in our lab, enabling swift stakeholder approval prior to mobilisation. This proactive approach reduced preparation time and uncertainty offshore.

The operation used a recirculating jet mixing and pumping system (RJM), combined with Ordinary Portland Cement grout and DNV-certified full-cement silos to ensure consistent, high-quality grout production and delivery. Our modern fleet and robust supplier network across Ireland and Europe ensured reliability and minimal breakdown risk. Close collaboration between onshore and offshore teams enabled tight coordination, while the equipment design supported efficient, high-standard grout mixing, transport, and installation. 

This integrated solution met safety, quality, and timeline goals, delivering the grouted foundation connection on schedule and to client requirements. 

Innovations in action

  • Recirculating jet mixing & pumping system (RJM)
  • Ordinary Portland Cement grout designed and approved in advance
  • DNV-certified full cement silos for efficient, safe offshore use
  • Pre-deployment laboratory mix validation to expedite offshore approval 

The result  

We completed the offshore grouting operation successfully within an eight-week preparation phase. The pre-approved grout mix, supported by reliable equipment and close coordination, enabled efficient mobilization and installation. Modern fleet assets and strong supplier partnerships minimised risk and delivery delays. Overall, the solution ensured a high-quality, bonded foundation connection that enhanced safety, saved time, and avoided resource waste. 

Related case studies

Discover more integrated marine foundation installation projects 

Case Studies

02 Apr 2026

Integrated marine foundations solution delivered for offshore mooring pile installation in Congo

Acteon’s Menck and 2H delivered a full offshore drilling and grouting service for eight mooring piles, supporting the Scarabeo 5 marine foundations project in Congo.

Case Studies

05 Feb 2026

Largest offshore grout pour to date delivered at Yeu-Noirmoutier Wind Farm

Menck, Acteon’s Marine Foundations business line, delivered its largest offshore grouting operation to date for DEME, supporting the installation of 61 turbine foundations at the Yeu-Noirmoutier Offshore Wind Farm. To keep pace with DEME’s rapid installation schedule, we executed large annulus grouting operations at previously unmatched pumping rates, achieving exceptionally fast turnaround times between pours and enabling fast consecutive foundation installations.

Case Studies

29 Jan 2026

Integrated offshore jacket installation and foundation solution in the Republic of Congo

Menck, Acteon’s Marine Foundations business line, delivered a fully integrated jacket installation solution for the Congo LNG project in 27 m water depth. The project required precise execution in a challenging marine environment. Tight tolerances, complex logistics, and remote coordination added pressure to deliver a safe, first-time-right installation.

Speak to our team

Our team of experts will design a solution that fits the technical, environmental and commercial demands of offshore projects.