Largest offshore grout pour to date delivered at Yeu-Noirmoutier Wind Farm

05 Feb 2026 1 minute 50 seconds

Aerial view of a grouting project taking place for DEME at Yeu-Noirmoutier Wind Farm

Project overview

Project name

Yeu-Noirmoutier Offshore Wind Farm

Location

Bay of Biscay, France, 16.5 km offshore

Developer partners

DEME

Solution

XL Monopile grouting solution

Menck*, Acteon’s Marine Foundations business line, delivered its largest offshore grouting operation to date for DEME, supporting the installation of 61 turbine foundations at the Yeu-Noirmoutier Offshore Wind Farm. 

Navigating a critical phase  

To keep pace with DEME’s rapid installation schedule, we executed large annulus grouting operations at previously unmatched pumping rates, achieving exceptionally fast turnaround times between pours and enabling fast consecutive foundation installations. 

Our solution

01High-volume monopile grouting solution

High-volume monopile grouting solution

Building on experience from the Saint-Nazaire project and leveraging new equipment innovations, we deployed our XL Monopile Grouting Package to meet Yeu-Noirmoutier’s scale and speed requirements.  

The package featured two automated planetary batch mixers, auger-fed from four 125 tonne silos. With over 500 tonnes of grout stored offshore and additional Sika Grout 9650 transferred to silos during operations, continuous mixing was maintained throughout each pour. An integrated automated wash system enabled a reduction of cleaning and preparation time between operations. Strong grout installation results were achieved through a high mixing rate, innovative implementations and consistent reliability.  

The solution integrated seamlessly with DEME’s MODIGA installation process, supported by jointly developed procedures and offshore service readiness. This enabled the installation of two turbine foundations within five days. The performance demonstrated Acteon’s capacity to deliver large-scale marine foundation projects reliably and efficiently.

Grouted connections work on the Noirmoutier offshore wind farm
02Innovations in action

Innovations in action

  • 100 m³/hr XL Twin Pan automated batch mixing system
  • Four 125-tonne grout silos (500-tonne total capacity)
  • Continuous SG9650 grout transfer during pumping
  • Two high-flow offshore grout pumps
  • Automated mixer and hopper wash-down system
  • Offshore lab with temperature-controlled sample storage
  • Dedicated offshore service and maintenance workshop 
Noirmoutier offshore wind farm suction piles grouting

The result

We delivered our largest grout pours to date with unmatched mixing speed, reliability, and operational readiness. The XL Monopile Grouting Package enabled DEME to maintain high foundation installation rates, completing two turbine foundations in just five days. The equipment sets new benchmarks for offshore grouting performance and reinforced Acteon’s position as a leader in marine foundations technology. 

*originally contracted through LDD 

Acteon’s performance on the Yeu-Noirmoutier Offshore Wind Farm project was outstanding. Their ability to deliver high grout volumes with exceptional reliability and speed was critical to maintaining our fast installation rate. The XL Monopile Grouting Package, jointly improved for this job based on Saint-Nazaire, is unmatched in the market and again integrated seamlessly with our MODIGA installation process. Their team's professionalism and technical expertise made a real difference, and we’re extremely pleased with the results.

Guillaume Fallourd, Project Manager DEME

Related case studies

Explore more Integrated marine foundation installation solutions projects

Case Studies

02 Apr 2026

Integrated marine foundations solution delivered for offshore mooring pile installation in Congo

Acteon’s Menck and 2H delivered a full offshore drilling and grouting service for eight mooring piles, supporting the Scarabeo 5 marine foundations project in Congo.

Case Studies

29 Jan 2026

Integrated offshore jacket installation and foundation solution in the Republic of Congo

Menck, Acteon’s Marine Foundations business line, delivered a fully integrated jacket installation solution for the Congo LNG project in 27 m water depth. The project required precise execution in a challenging marine environment. Tight tolerances, complex logistics, and remote coordination added pressure to deliver a safe, first-time-right installation.

Case Studies

20 Mar 2025

Seamless integration: Acteon's North Sea grouting operation success

Menck, Acteon’s Marine Foundations business line delivered offshore grouting services to install a wellhead platform foundation and four-legged jacket with driven foundation piles in the North Sea.