Project overview

Project name:

Petrojarl 1

Location:

Santos Basin | Brazil

Developer partners:

Altera

Water depth:

1,500 m

Solution:

FPSO decommissioning

Intermoor, Acteon’s Moorings and Anchors business line, executed a multi-phase offshore decommissioning campaign for Petrojarl I FPSO offshore Brazil. 

Overcoming technical complexity in deepwater

The decommissioning of FPSO Petrojarl I presented several technical challenges due to the age of the asset and demanding offshore conditions. In parallel, continuous station keeping and heading control of the FPSO were critical during riser and mooring line disconnection activities. 

Our solution

01Early identification of risks and flawless execution

Early identification of risks and flawless execution

The first phase included the provision of engineering for pull-in wire replacement, risers pull-out, mooring line disconnection, including a contingency plan of non-operability of mooring winches and the FPSO towing preparation and tow plan. 

Subsequently, the mooring system removal required the recovery of eight mooring lines in approximately 1,500 m of water, which added substantial operational and logistical complexity. The campaign also involved the replacement of a 3.5-inch pull in wire and the spooling of 16 sections of polyester rope, each 4.5 inches in diameter and 1,100 m in length, demanding careful handling, sequencing, and equipment coordination. 

And finally, the team was involved in the towing of the asset to Las Palmas. 

View from Petrojarl 1 FPSO offshore Santos Basin, Brazil
02Working at scale

Working at scale

Our team provided locally: 

  • Up to six Mooring Masters and Tow Master offshore simultaneously  
  • 150-ton spooling machine 
  • Surface positioning survey for three assets  
  • Equipment such as chain, connecting links and J-lock 
Offshore staff assembling a spooling unit offshore on the Petrojarl 1 FPSO offshore Santos Basin, Brazil

The result

The project delivered significant benefits, including the early identification of risks that enabled:  

  • effective mitigation well ahead of offshore execution,  
  • a flawless safety record with no injuries,  
  • successful completion of the full decommissioning scope,  

and minimised offshore downtime and avoided costly schedule delays.  

These outcomes were achieved through a comprehensive planning phase that addressed all potential offshore scenarios, ranging from weather impacts and vessel logistics to mooring contingencies and equipment readiness. At the same time, the team ensured seamless coordination between engineering, operations, and marine assets, ultimately demonstrating the capability to deliver complex offshore projects from concept engineering through to completion. 

Related case studies

Explore more decommissioning projects 

Case Studies

12 Sep 2025

Floating Storage and Offloading (FSO) disconnection, removal and towing

Intermoor, Acteon’s Moorings and Anchors business line, completed the disconnection, removal, and towing of a 20-year old FSO vessel in the Gulf of Thailand.

Case Studies

17 Jul 2025

Seamless pipeline tie-in decommissioning and asset transfer

Intermoor delivered 46 complex pipeline tie-in disconnections, asset recoveries, and wet storage operations across multiple offshore fields for a major Southeast Asia energy operator.

Case Studies

11 Jul 2019

From mooring to decommissioning with a deepwater FPU

Intermoor provided end-to-end mooring services for an FPU in the Gulf of Mexico, from installation to safe decommissioning over an eight-year period.

Speak to our team

Our team of experts will design a solution that fits the technical, environmental and commercial demands of offshore projects.