Complex FPSO top chain replacement completed safely and efficiently

28 Jan 2025

Intermoor completing a top chain change-out on an FPSO

Project overview

Project overview

Mooring system maintenance

Location

North Sea

Solution

Mooring line top chain replacement

Intermoor, Acteon’s Moorings and Anchors business line, supported a major North Sea operator with project management, planning and offshore support for planned maintenance on its floating production, storage, and offloading (FPSO) vessel.

Ensuring operational integrity

We replaced the winch wire, three mooring line top chains and assessed the condition of the recovered chains. The work was complicated by large equipment sizes, tight design tolerances and restricted space, requiring precise execution under challenging conditions.

Delivering efficient mooring system upgrades through technical precision

Restricted space required a complex wire transfer with tight tolerances between an anchor handling vessel (AHV) and the FPSO to avoid bringing heavy machinery on-board.

The top chain changeout involved simultaneous operations (SIMOPS) across four vessels, handling of a large 152-mm chain and associated ancillaries, and executing a like-for-like system replacement.

Our onshore team provided detailed analysis and planning to support our experienced offshore tow masters and marine representatives, enabling tight heading control throughout. Our technical expertise in chain handling allowed us to develop procedures to maximise the use of mechanical aids, prioritising personnel and equipment safety.

Our collaboration with a specialist chain test house ensured that all components met target loading criteria, supporting long-term integrity planning and potential life extension of the existing mooring system-reducing the need for new component manufacturing.

The result

The operation was completed safely, on time and fully in line with regulatory and client expectations. Our expertise in complex offshore projects and SIMOPs enabled seamless execution while minimising project footprint and without interrupting production. The FPSO’s mooring system was successfully restored, improving operational confidence and lifecycle value.

Related case studies

Explore more mooring integrity management projects

Case Studies

01 Jul 2025

Innovative chain replacement method supports Bonga’s life extension project

Intermoor replaced the top chain on all twelve mooring lines (four groups of three) of the Bonga FPSO, located 120 km southwest of the Niger Delta.

Case Studies

14 May 2025

Fast and reliable mooring line repair on an FPSO

Intermoor carried out a successful emergency mooring intervention on a 10-year-old Floating Production Storage and Offloading (FPSO) offshore Brazil.

Case Studies

13 Feb 2024

Uninterrupted production during mooring line top wire replacement

Intermoor delivered a full-scope top wire replacement for a 57-year-old offshore platform in Brazil, completing the operation safely in just 45 hours, without disrupting production.

Speak to our team

Our team of experts will design a solution that fits the technical, environmental and commercial demands of offshore projects.